Power · Completed
Hydro bins, CW pipelines, pump-house piping and vertical pump erection.
- Client
- BGR Energy Systems
- Location
- Ibrahimpatnam, Krishna District, Andhra Pradesh
- Duration
- 2006 – 2011
- Status
- Completed
- Capacity
- 1 × 500 MW
- Sector
- Power
The project
About the project
At VTPS Stage IV, close to our home in Ibrahimpatnam, KVK Industries fabricated and erected 14 m × 0.7 m hydro bin cells and hoppers, and executed the circulating-water (CW) pipelines in the condenser and pump-house areas — including large meter bends.
The package also covered vertical pump erection and LP pipelines in the pump house, completed between 2008 and 2009.