TPCIL 2 × 660 MW Thermal Power Plant — Nellore

Power · Completed

TG erection for Units 1 & 2, with fire-fighting and ACW pipelines.
Client
BGR Energy Systems
Location
Nellore, Andhra Pradesh
Duration
2012 – 2015
Status
Completed
Capacity
2 × 660 MW
Sector
Power

The project

About the project

For BGR Energy Systems at the 2 × 660 MW TPCIL plant in Nellore (the Gayatri power project), KVK Industries carried out turbine-generator structural erection for both units, together with the plant’s fire-fighting and auxiliary cooling water (ACW) pipelines.

On site

5 photographs

Next project

Power /2009 – 2018 /Tata Projects

Start a conversation